Street Projects

HedgerowConstruction

Phasing

Phase 1 will start on Nov. 28th at 8am. The entire street from 45th to the center of the intersection of 47th will be shutdown at this time. Please have all vehicles out of this area at this time. There will be no way to get vehicles into or out of this area until the end of the project. During this phase, residents north of 47th will still be able to access their homes using the north half of the 47th street intersection.


Phase 2 will start 3-5 working days after the start of phase 1. Residents in this phase will be given 24 hrs. notice of the closing to remove their vehicles. Once the street is closed, there will be no way to get vehicles into or out of this area until the project is complete.


Phase 3 will be the paving of the entire project from 45th street to the north end. After sufficient cure time we will reopen the street. We anticipate the entire project taking approximately 3 weeks.

View highlighted phasing map here.

Temporary Parking

Sunrise Academy has been gracious enough to allow for parking on some of their adjacent properties. These areas are identified on a parking map which you can view here. There are some of these areas that are a grass or dirt surface. We ask that you please refrain from using them if it is wet and muddy.

Trash Service

Andale Construction will pick up your trash container at 7am the morning of normal trash pick up and take them to the corner of 47th and Hedgerow to be emptied. We will return them sometime that afternoon.

Mail Delivery

Your mail will be held at the post office for pickup for the duration of the project.


Questions or concerns during the project, please call 316-249-1914.